Calculate How Many Paving Slabs You Need
A patio is two numbers on a merchant's ticket: how many paving slabs, and how much sharp sand sits under them. The slab count carries a waste allowance for edge cuts. The bedding volume does not — it follows the real footprint, not the offcuts in the skip.
Size, waste, bed depth: the form takes those as given. What follows is the build underneath — falls, joints, edging — the part a 15 m² rectangle never shows on its own.
Dimensions and materials
An asterisk after a trade term opens its definition in the glossary at the end of the article.
Bedding on sharp sand, mortar, or pedestals
Three builds, and they do not share a rectangle. Sand leaking from under a mortar-bedded flag, or a pedestal* punching into soil next to a neighbour that sits on Type 1, is how a patio opens in year two.
- Sharp sand on compacted Type 1 — the back-garden patio. MOT Type 1* (or a similar hardcore) well compacted in layers, geotextile on the formation, then 30 to 50 mm of sharp sand*. Flags go on the sand, tapped to line. Cheap, proven, and useless without edging and a fall.
- Mortar bed on a slab — rigid paving. Concrete already in place, or a surface that has to take a car. Flags buttered or laid on a full bed. Permanent. Lifting it later means a breaker.
- Pedestals — balcony, roof terrace, a deck that must not be punctured. No sand. Each slab sits on four heads; rain runs underneath to the outlets. Dearer per square metre. The right answer the moment a waterproofing membrane is in play.
Type 1 is not the bedding. It is the load-bearing layer, typically 100 mm in a garden, thicker on clay or in a frost hollow. The sand is only a finishing coat. Order 0.75 m³ of sand and then discover another 1.5 m³ of stone is missing, and the job stalls on a Tuesday. A garden patio is sand on Type 1. A flat roof is pedestals. Mortar is for when the concrete is already there, or when the surface has to be locked down.
Falls: a patio is never laid dead level
Water that sits on flags turns them green. A January frost then pops the joint. A patio photographed “dead level” on handover is, three storms later, a moss tray against the house wall — exactly where the water should never have stopped.
British paving wants a fall* of about 1:80 to 1:60 — 12 to 17 mm per metre — away from the house, towards a channel, a gully, or the lawn. Gentle enough that a table does not look drunk. Steeper than 1:30 and the slope shows, and chairs creep. Five metres of patio at 1:80 is a 62 mm drop: a spirit level barely notices, a bucket of water does.
drop (mm) = length (m) × 1000 / 80 · 5 m patio at 1:80 → 62 mm
Percentage, degrees, a 1:n ratio: that conversion is the slope calculator. This page only needs a continuous drop, one way, from the bifold threshold to the low edge. Pedestals are not tilted with the structure. The low-side heads are wound down a turn. On sand, the fall is set in the Type 1, not raked into the bedding after the first row is down.
Level for furniture is not zero fall. It is a quiet 1:80 that a spirit level barely shows and a puddle cannot argue with.
Joint widths and what goes in them
The joint is working, not decorative. It takes summer expansion, lets a little water through, and stops two arrises chipping each other to bits. Flags butted tight in July split their edges. Flags with a 20 mm gap stop being a patio and start being a yard.
Most concrete and porcelain flags sit happily at 3 to 5 mm. Tighter and they kiss in a heatwave. Wider and the pointing looks agricultural. Riven natural stone wants more: the gauge is not the same twice, and 8 to 12 mm looks honest on Indian sandstone where it would look sloppy on calibrated porcelain.
- Kiln-dried sand, brushed in — the old patio job. Cheap. It walks out if the fall is lazy.
- Jointing compound / polymeric sand* — brush, mist, wait. Stays put, and it drains. What pointing a modern patio usually means.
- Resin or mortar pointing — hard, tidy, not cheap. Porcelain, pool surrounds, a path that sees boots every day.
A 4 mm polymeric joint, properly wetted, outlasts a cement-only smear that stains the face and then cracks. Neat cement in the joint is a stain waiting to happen. Around a swimming pool the resin joint is almost the default — chlorine and wet feet do not forgive loose sand — while the volume of the pool itself is a separate take-off, done before anyone talks flags.
Adjustable pedestals without a sand bed
No bedding layer. Four supports to a slab, five on a large 600 if the manufacturer says so. Dial the head, lay, move on. The void underneath ventilates, drains, and stays useful: two slabs lift and a pipe is reachable.
That said, the deck underneath has to carry the load. Pedestals on soft ground sink, slab by slab, until the plane looks like corrugated sheet. Pedestals on a membrane need spreader pads — never a screw through the felt, never a staple “to hold the foot”. Pedestal height plus slab thickness is settled before the bifold threshold is ordered. Too high, and a step has been built into the living room, with the door scraping the sill that has just gone in.
The sand volume on this page then goes to zero. The count is pedestals — four per slab, plus the perimeter, plus cuts — not cubic metres. Sixty 600 × 600 flags on 15 m², before waste, is already 240 heads. The quote changes column.
Decking is a different take-off
Boards sit on joists, with a gap at the ends, hidden clips or screws, and a fall along or across the boards depending on the system. That is a timber floor, not a tiled rectangle. The quantities do not travel.
Waste is no longer 10 %. Decking often wants 12 to 15 % — ends, mitres, a starter board too skinny to look like a board. Then the joists, the pedestals or packers, the fascia, sometimes a double frame. This calculator does none of that. A square metre of flags is not a square metre of boards, in price, in weight, or in fall.
Geotextile under the MOT Type 1
A permeable geotextile, rolled out on the formation, under the Type 1. It stops clay pumping up into the stone and sand washing down into the clay. Skip it and, come May, the dandelion finds the joint — not by magic, by the void the aggregate left and the fines that travelled.
Turn it up at the edging, overlap sheets by 200 mm, cover the whole rectangle. Not the flimsy weed-control fabric from a garden-centre trolley. Aim for 100 g/m², 150 if the ground is hungry. Order 20 m² of membrane for a 15 m² patio: the upstand folds, it is not trimmed flush. A sheet cut to the kerb line shrinks at the first soaking and leaves a gap the clay will use.
Pedestals do not sit on garden geotextile. The roof membrane is another animal, and it is not stapled. Mixing the two sheets is how a weed fabric gets treated as waterproofing, or a felt as a filter.
Edge restraints that keep the bed in
Sharp sand has no loyalty. Without an edge restraint the first row opens, the bed leaks, and the perimeter flags tip. Classic failure, eighteen months after a job that photographed well. The middle still looks fine. The edge has already dropped a centimetre.
- Concrete kerb or block, haunched* in concrete — the garden default.
- Steel, aluminium, corten — thinner, fine if the sub-base is solid.
- A channel drain on the low side — restraint and an outlet in one piece.
Edging goes in before the bedding, to line and to the fall. Perimeter is 2 × (L + W). A 5 × 3 m patio is 16 m of restraint. This page does not add it to the ticket. It is a linear extra, with its own concrete. Edging dropped in after the flags restrain nothing.
Worked example: 15 m² in 600 mm flags
A 5.00 × 3.00 m rectangle. 600 × 600 mm flags — the size most UK merchants actually have on the yard. 10 % cutting waste, 50 mm of sharp sand. The arithmetic is the one this page runs if the form is left alone, except the default 50 × 50 in the fields is swapped for the 600 that the yard actually sells.
- Area = 5 × 3 = 15.0 m².
- One slab = 0.60 × 0.60 = 0.36 m².
- Slabs = round up(15 × 1.10 / 0.36) = round up(45.83) = 46 slabs.
- Bedding volume = 15 × 0.05 = 0.75 m³ of sand (no waste on the bed: it follows the real footprint).
- Indicative weight = 0.75 × 1.5 ≈ 1.1 t.
ceil(15 × 1.10 / 0.36) = 46 · 15 × 0.05 = 0.75 m³
The Type 1 is not in the result. 100 mm over 15 m² is another 1.5 m³, and that is the load that sits on the formation. The 46 slabs are honest on a clean rectangle. A curve, a tree, a barbecue plinth, and the 10 % is gone — 15 % once a re-entrant corner appears.
600 mm flags versus 450 mm
600 × 600 is fewer joints and a heavier lift. A concrete 600 often weighs 20 to 25 kg. 5.00 m is not a multiple of 0.60, so one edge will be a cut strip — 200 mm if the joints are generous, more if they are tight. 400 × 400 flips it: ceil(16.5 / 0.16) = 104 pieces, more pointing, easier to carry, less leftover on an awkward length. 450 × 450 sits in the middle, a familiar size on older British patios, and it almost grids a 5 × 3 m plot.
A size is not chosen so that it “comes out exact”. The look is chosen, then the cuts are paid for. A grid on paper, before the merchant is phoned, saves a pallet too many — or a pallet too few, on a Saturday at four.
Frost heave and the sub-base
Water left in the hardcore freezes. Ice lifts the edge, the slab clicks, and after the thaw the void remains. That is frost heave*, and it loves a thin, wet, unedged patio. In a low-lying English garden one winter is enough. In a Scottish hollow the same thin bed does not see spring.
The usual defence is boring: a real fall, Type 1 that actually drains (not clayey scalpings from the last job), geotextile, haunched edging, joints that let water out. In a frost hollow the sub-base thickens — 150 mm is not a luxury. Whacking a 30 mm sand bed harder will not freeze-proof it. Saturated sand under a thin flag works all winter, and spring presents the bill in cracked slabs.
A roof terrace is not a soakaway
In the garden, water disappears into the ground. On a roof it has only the outlets. Pedestals, a fall in the screed towards the gullies, an overflow, and open joints so rain reaches the membrane instead of ponding on the flags. A roof terrace is not a soakaway.
Fifty millimetres of sand is not tipped onto a felt. Nothing is drilled. Pedestals sit on pads, sometimes on a protection board. Maintenance means a slab can be lifted and the outlet cleared — hence open joints, never a bonded pointing that seals the access. If this calculator prints a bedding volume, that volume does not apply up here: there is no bed.
Live load on a balcony
A 40 mm concrete flag is not the same dead load as 20 mm porcelain. Add planters, a table, six people. Domestic balconies in the UK are often checked around 2.5 kN/m² imposed — a yardstick, not a licence to stack anything. Fifty millimetres of saturated sand already sits near 80 kg/m², before the flag, before the olive trough.
The slab count says nothing about the structure. Before 50 mm of sand, flags and troughs land on an existing balcony, the permitted load is checked. Otherwise the build stays on pedestals, the flags stay thin, and the water — and the weight — go where the engineer sent them.
Glossary
- Pedestal
- An adjustable support, plastic or concrete, under the corner of a paving slab. Four per slab in ordinary use. The head screw sets the height, and therefore the fall, with no sand bed.
- MOT Type 1
- A graded crushed-rock sub-base (often 40 mm down to dust) specified for roads and widely used under patios. Compacted in layers, it carries the load. It is not the sharp-sand bedding on top.
- Sharp sand
- Coarse, gritty building sand used as a 30–50 mm bedding layer under flags. Not play sand, not soft bricklaying sand: those hold water and do not drain.
- Fall
- The slope that takes rain off a patio, usually written as a ratio (1:80) rather than a percentage. Away from the house, towards a channel, a gully or the lawn. Zero fall is a tray.
- Polymeric sand
- Jointing sand with a binder that sets when misted. Brushed into the joints, it hardens while remaining slightly permeable. More durable than loose kiln-dried sand, less rigid than a resin joint.
- Haunching
- A wedge of concrete behind and under an edge kerb, locking it against the sub-base so the first row of flags cannot spread. Edging without haunching is decoration.
- Frost heave
- Lifting of the edge flags when water in the sub-base freezes and expands. After the thaw the void remains. Typical causes: no fall, no edging, a thin wet bed.