A roof's area is never the same as the building's footprint: the pitch stretches it out. It's this real area — the area of the roof slopes — that determines rafter lengths and the number of tiles or slates to order. The roof type, the building dimensions and the pitch give both at once.
Just need to convert a pitch between percent, degrees and ratio? Our slope calculator does that alone, with a roof-pitch classification and a ramp-accessibility check.
Dimensions and covering
Trade terms marked with an asterisk are spelled out in the glossary at the end of the article.
Pitch first: why the plan area never buys the covering
A roof is not a floor. The pitch* stretches every metre of covering. British merchants still think in degrees — 22.5°, 30°, 35°, 40° — more often than in percent. Thirty-five percent, the default on this form, is only about 19°. That is a shallow interlocking-tile pitch in UK practice; BS 5534 more often starts a concrete tile at 17.5° or 22.5°, depending on the lap.
Divide the plan area by the cosine of the angle and the slope area appears. Skip the cosine and the last course will not close. At 22.5° the shortfall is already 8%. At 45° it is 41%. A laser run along a rafter already in place is the slope length; no further division. That is a reroof. A drawing still on paper needs the cosine, overhang included.
Percent, degrees and rise-over-run are the same slope written three ways. Converting them, without mixing in square metres, is the job of the slope calculator.
Rafter, purlin and principal rafter
The common rafter* follows the pitch. Battens and the covering sit on it. Its length is the slope length this page returns — not the building width on plan. Order timber from a tiling take-off and the sticks arrive short, or the pallet of tiles arrives light.
A purlin* runs level, ridge to eaves in direction of the span, and takes the rafters between trusses or gable walls. Wall plate at the foot, ridge board or ridge purlin at the top, an intermediate purlin if the span asks for one. The principal rafter* is not another common rafter. It is the sloping member of a traditional truss, framed with a tie beam below and, often, a king post at the peak. Principals come in pairs. Common rafters are counted along the ridge.
None of those sections is sized here. The page measures the skin: rafter length, area, quantity of covering. A tile count does not say whether 47 × 150 C16 will do, or whether 47 × 200 C24 is the next call.
Cut roof versus trussed rafters
A cut roof is carpenter's timber, assembled on site. The loft often stays open; a room-in-roof is possible if the height under the ridge allows it. More labour, more cost, a volume that can still be lived in.
Factory trusses arrive as triangles — Fink, attic, mono — usually at 600 mm centres. Fast. Cheap. The loft fills with webbing and becomes storage, unless an attic truss was on the order from day one. BS 5268 is the old timber code; Eurocode 5 is the current one. Neither is a tiling standard.
The covering area does not care which family is under it. Tiles, slates, profiled sheet: once pitch and overhang are known, the slope is the same rectangle. What does change is access (walk or crawl), how much insulation will fit, and where the pallets sit on delivery day. Choosing the frame is not choosing the tile count. It is choosing what remains underneath.
Span, centres and the size of a rafter
Four numbers, not one. Span between bearings, centres, load (dead load of the covering, snow, wind) and grade. A 47 × 100 at 400 mm centres is not a 47 × 200 at 600. The first may carry a felted shed. The second starts to carry a tiled house with insulation between the rafters.
TRADA span tables, the merchant's chart, Eurocode 5: those beat “we have always used four-by-two”. A plain-tile roof at sixty pieces a square metre weighs differently from a standing-seam sheet. A Scottish snow load is not a southern English one. This page does not replace the tables. It gives the length to cut, not the section to pick.
Rafter centres and batten gauge are not the same spacing. One belongs to the structure. The other belongs to the covering, read off the product sheet. Mix them and tiles land on timber that is not there — or rafters get packed in “so the tiles have something to sit on”.
Hip and valley work this form does not do
One pitch or two: that is the calculator. A hip* roof has four slopes. The gables go; triangles (or trapeziums, if the hip is not full) take their place. Each surface is taken off on its own. The hip rafters, those proud arrises, add timber and multiply the cuts.
A valley* is the opposite: two slopes meeting in a hollow. Water concentrates there. Lead, a valley trough, or a tiled valley, and a bigger lap. Treat a valley as two rectangles butted together and both the metal and the waste come out short. A dormer, a sprocket at the eaves, a side abutment: add them afterwards, piece by piece. A 6 × 4 rectangle is not a hip. Nothing stops a complex roof being split into several pitch calculations and then added up — provided the hips and valleys are stuck on by hand.
Tiles versus slates: lap, gauge, laying direction
A tile does not occupy its nominal area. It laps the one below, and often the one beside it. Lap eats material: 10 to 15% over the net slope is common, before verge, ridge and cuts. A large interlocking concrete tile sits around 9.5 to 12 pieces a square metre. A plain tile, closer to 60. Natural slate, depending on the gauge, often around 20. Those rates on the form are orders of magnitude. The manufacturer's sheet for the chosen model is the rate to type into “custom”.
Laying starts on the side away from the driving rain, so the side lap turns its back to wind-blown water. Battens are fixed at the gauge* on the product sheet, not “every 300 mm because it is a round number”. Too tight a gauge and the lap smothers. Too open and the joint shows. In practice the batten take-off is ridge length times the number of courses — a separate count, which this page does not make.
Tiles and slates are not interchangeable on the same batten gauge, nor on the same minimum pitch. A slate roof that is happy at 40° will not take a large concrete interlocking tile at 15° without a specified underlay and a specified lap. The covering drop-down on the form is a reminder of that, not a design check.
Underlay once the pitch is tight
Once the pitch is at the product minimum, or the site is exposed, a breathable underlay* is the rule, not an extra. BS 5534 treats underlay as part of the system. A slipped tile with nothing beneath it is wet insulation the next morning.
A low-resistance (LR) underlay lets vapour from the house out and keeps rain out. A sheet of damp-proof polythene under the rafters does the opposite. Vapour stops, condenses, and the timber rots quietly. The membrane is laid taut over the rafters, laps sealed, before counter-battens that keep the air path under the tiling battens. That said, an HR underlay (bituminous felt of the old school) still turns up on reroofs; it needs a ventilated batten cavity more carefully than an LR sheet does.
Cold loft or insulation between the rafters
Two tactics, one winter. A cold loft: quilt on the ceiling joists, U-value down toward 0.16 W/(m²·K) in new work under Part L, often lower if a grant is in play. It is the cheapest kilowatt-hour in the house — a thick quilt, a continuous ceiling, no cutting around every rafter. A warm roof, or a room-in-roof, puts the insulation between and usually under the rafters, with a vapour control layer on the warm side and, where the covering requires it, a ventilated gap under the battens.
The choice is architectural before it is thermal. A loft that will be lived in forces the insulation into the slope. A loft left as storage leaves it on the ceiling. This page returns square metres of covering, not of quilt. The thickness that matches a target R-value is a different sum: the thermal-resistance calculator for a wall or roof build-up stacks the layers, λ included.
Worked take-off for a 6 × 4 m garage
A rectangular garage, 6 m along the ridge, 4 m span, two pitches at 35%. Plan area: 24 m². That is not the area to cover.
Angle α is arctan(0.35) ≈ 19.3°. Cosine of 19.3° ≈ 0.944. With no overhang, slope area is plan divided by that cosine: 24 / 0.944 ≈ 25.4 m². With a 500 mm overhang on all four sides — the form's working assumption — the ridge becomes 7 m, the rafter run 2.50 m, the rafter length 2.65 m, and the total area about 37 m². On a small building the overhang, at bottom, moves the order more than the pitch does.
Aslope = Aplan / cos α · with overhang: A = 2 × (L + 2d) × ((ℓ/2 + d) / cos α)
Ten percent waste: 28 m² to order without overhang, 41 m² with. Interlocking tile at 10 pieces/m²: 280 in the first case, 410 in the second, then round up to the pack. Merchants sell by the 20 m² stillage or the 240-tile band, rarely by the piece. A leftover on the floor beats a missing course at the verge.
A tile take-off is not a roof design. Snow, wind, section, connections: a carpenter, or an engineer. The calculator is a sound estimate for a simple rectangle of one or two pitches; a hip, a valley or a dormer wants its own survey.
Ridge, verge and the fittings the square metre never buys
Net slope does not purchase the fittings. Ridge tiles are counted by the metre, plus stops. Verges follow the rafter length on each gable. Dry-ridge kits, abutment soakers, hip tiles if a hip appears, valley troughs if two pitches cross: those sit in another column of the quote.
The 6 × 4 garage, no overhang: 6 m of ridge, two verges of about 2.1 m on each pitch, some 8.5 m of verge in all. With overhang, ridge 7 m and verges 2.65 m. They go on the quote, not into the square metres of slope. A dry ridge left off the list shows from the garden. A verge tile left off the list shows in the rain.
Overhang, sprocket and gutter
The overhang is not decoration. It throws water off the wall, shelters the render, carries the gutter. Five hundred millimetres is a common new-build figure. Zero is a gable sometimes, a lean-to against an existing wall, a value the form will take. Past a metre the rafter cantilevers in earnest: section, fixing, and often a sprocket.
A sprocket is the short extra at the foot of the rafter that eases the pitch at the eaves. It adds a couple of hundred millimetres, sometimes more, and breaks the straight line the calculation assumes. A gutter, even so, is sized on the slope that feeds it, not on the plan area: a longer rafter means a sharper peak flow. The form ignores sprocket and gutter section. It only sees the overhang typed in, the same on all four sides — fair for a simple rectangle, thin once an eave overshoots a gable.
Glossary
- Pitch
- The slope of the roof, stated in degrees, as a percentage, or as a rise-over-run ratio. It sets both the rafter length and the minimum covering that will still shed water.
- Rafter
- The common sloping member, from wall plate (or eaves) to ridge. It carries battens and covering. Its length is the slope length.
- Purlin
- A horizontal member that supports the rafters between trusses or gable walls. Wall plate at the foot, ridge at the top, intermediates if the span needs them.
- Principal rafter
- The sloping member of a traditional (cut) truss, framed with a tie beam and often a king post. It is not a common rafter; it is the truss itself, in pairs.
- Underlay
- The sheet laid over the rafters before the battens. A low-resistance (breathable) underlay lets vapour out and keeps rain out. A polythene vapour barrier used in its place traps moisture.
- Hip
- The external arris where two slopes meet, and by extension a four-slope roof that replaces the gables with triangular ends. Hip rafters and hip tiles belong here.
- Valley
- The internal gutter where two slopes meet. Water concentrates; lead, a trough, or a tiled valley is used, with extra lap and extra waste.
- Gauge
- The spacing of tiling or slating battens, set by the product's head-lap. It is not the same as rafter centres.